Report for August 2014
- Report Date
- August 2014
Achievements in Last Period
- LEARN feed successfully tested
- Group changes tested after several attempts
Issues
- Continuing problems with Group changes in LEARN
- Lack of quality test data hampered testing
- Project reported as Red because changes have still not been implemented into LIVE
Next Steps
- Deliver the Learn outgoing feed into Live
- Project closure
Milestones
29-Aug-2014 | 20-Aug-2014 | Outgoing Interface Switchovers Documented and Tested | Integrate |
05-Sep-2014 | 27-Aug-2014 | Project Closed | Close |
- Approved budget
- 77.0 days
- Activity this month
- 5.1 days
- Activity this year
- 5.1 days
- Activity to date
- 78.0 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days