Report for August 2014

Report Date
August 2014

Achievements in Last Period

  • LEARN feed successfully tested
  • Group changes tested after several attempts

Issues

  • Continuing problems with Group changes in LEARN
  • Lack of quality test data hampered testing
  • Project reported as Red because changes have still not been implemented into LIVE

Next Steps

  • Deliver the Learn outgoing feed into Live
  • Project closure

Milestones

29-Aug-201420-Aug-2014Outgoing Interface Switchovers Documented and TestedIntegrate
05-Sep-201427-Aug-2014Project ClosedClose

 

Project Status
Activity
Approved budget
77.0 days
Activity this month
5.1 days
Activity this year
5.1 days
Activity to date
78.0 days
Estimate to complete current year
1.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Annual Roll-Forward to 14/15
Code
TTU003
Programme
Timetabling (TTU)
Project Manager
David Watters
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Start Date
13-Sep-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
12-Sep-2014
Programme Priority
2
Overall Priority
Normal
Category
Compliance