Report for August 2022

Report Date
August 2022

Achievements

  • BI Reports Issue resolved following escalation. Dev Tech, Tech Management and Production Management staff worked to resolve to allow reports to be run off the new DB ahead of start of year. TLS 1.0 switched back on to accomodate this, will need to be resolved.

Issues

  • Supplier removing support for current versions of Enterprise Timetabler, Resource Booker and Exam Scheduler. New project started under TTU025
  • Supplier cancelled upgrade of CalSync in Exam Timetabling, rescheduled for 7th Sept.

Next Steps

  • Schedule Calsync upgrade in Exam Timetabling
  • Complete UTF5 Script
  • Prepare for closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
Within Tolerance
Scope
Within Tolerance
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
162.0 days
Activity this month
21.5 days
Activity this year
21.5 days
Activity to date
128.0 days
Estimate to complete current year
13.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Annual Roll-forward to 2022/23
Code
TTU023
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Oct-2021
Planning Date
22-Oct-2021
Delivery Date
29-Jul-2022
Close Date
08-Nov-2022
Programme Priority
1
Overall Priority
Highest
Category
Compliance