Report for September 2022

Report Date
September 2022

Achievements

  • CalSync Upgrade in Exam Scheduling LIVE

Issues

  • Supplier removing support for current versions of Enterprise Timetabler, Resource Booker and Exam Scheduler. New project started under TTU025
  • Supplier cancelled upgrade of CalSync in Exam Timetabling, rescheduled for 7th Sept.
  • TLS 1.0 switched back on to resolved reports issue affecting preparation for start of term, will need to be resolved.

Next Steps

  • Prepare for closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
Within Tolerance
Has formal escalation taken place?
No
Activity
Approved budget
162.0 days
Activity this month
6.7 days
Activity this year
28.2 days
Activity to date
134.7 days
Estimate to complete current year
13.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Timetabling Annual Roll-forward to 2022/23
Code
TTU023
Programme
Timetabling (TTU)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Scott Rosie
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
04-Oct-2021
Planning Date
22-Oct-2021
Delivery Date
29-Jul-2022
Close Date
08-Nov-2022
Programme Priority
1
Overall Priority
Highest
Category
Compliance

Documentation