As part of the School of Law refurbishment project the Law Library moved to David Hume Tower (DHT) in June 2016, and will transfer back to the refurbished space in Old College in Summer 2018.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
January 2019 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
New Law & Europa Library Project
Code
USD012
Programme
User Services (USD)
Management Office
ISG PMO
Project Manager
Elizabeth Stevenson
Project Sponsor
Elizabeth Stevenson
Current Stage
Close
Status
Closed
Start Date
13-Nov-2013
Planning Date
01-Aug-2011
Delivery Date
14-Jan-2019
Close Date
14-Jan-2019
Overall Priority
Normal

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.