Project Report for December 2024
- Report Date
- December 2024
Project Closure approved on 4th December 2024 at App Review
- Approved budget
- 75.0 days
- Activity this month
- 8.4 days
- Activity this year
- 26.9 days
- Activity to date
- 26.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 31.0 days