Project Report for December 2024

Report Date
December 2024

Project Closure approved on 4th December 2024 at App Review

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
75.0 days
Activity this month
8.4 days
Activity this year
26.9 days
Activity to date
26.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
31.0 days

Project Info

Project
IT & Library Business Service Readiness for Start of Semester 24/25
Code
USD034
Programme
ISG User Services (USD)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Neil Bruce
Current Stage
Close
Status
Closed
Start Date
01-Mar-2024
Planning Date
07-May-2024
Delivery Date
22-Nov-2024
Close Date
04-Dec-2024
Overall Priority
Highest

Documentation