Project Report for May 2024
- Report Date
- May 2024
Achievements this period
- Planning review Milestone completed
- Deputy PM onboarded
- ISG Representatives confirmed
- IT Readiness Strand tracker configured for 2024/25
- IT Readiness Strand meetings planned and started
- Recruitment for student interns completed
- The following milestones were achieved
Issues
- The project manager has been conflicted to work on the Web Publishing Platform Projects/programme. This has delayed progress with completing planning and resulted in the project remaining AMBER RAG.
Next Steps
- Start more detailed welcome week planning
- Complete purchasing where required
- Start comms on IT Readiness Strand
- Complete induction for project assistant interns
RAG Commentary
Issue: The project manager has been redeployed 2 days per week on the Web Publishing Platform Projects/programme.
Impact: This reduces the time the project manager can progress with planning and other project activities.
Next steps: The PM will continue to with with another PM to assist and project management and cover annual leave.
Project Milestones
Stage | Milestone | Due Date |
---|---|---|
Execute | IT & Library Readiness Weekly Reporting Begins | 05-Aug-2024 |
Execute | Welcome Week Planning Complete (D1.3, D1.4, D1.5a, D1.5b, D1.6, D1.8, D1.9, D1.10) | 19-Aug-2024 |
Execute | IT & Library Readiness Weekly Reporting Ends | 06-Sep-2024 |
Deliver | International Arrival and Start of Welcome Week (External Milestone) (D2.1) | 07-Sep-2024 |
Deliver | Start of Teaching Week 1 (External Milestone) | 18-Sep-2024 |
Deliver | Start of Teaching Week 2 (External Milestone) | 25-Sep-2024 |
Deliver | Delivery Sign Off Review following Start of Session | 17-Oct-2024 |
Close | Project Closure | 02-Dec-2024 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days