Project Report for July 2024
- Report Date
- July 2024
Achievements this period
- Detailed Welcome Week Planning well underway
- Comms on IT Readiness: the drafts have been approved by the stakeholders and approved
- Online Students: complete
- Experiential: activities confirmed and planning in progress
- Social Media: the strategy draft shared on Sharepoint, filming in progress
- All key purchasing activity completed
- Video production for social media has started
Issues
- No issues so far
Next Steps
- Complete purchasing for smaller items
- Finalise the activities for Comms on IT Readiness (done for most part)
- Complete video production across all workstreams
- Social media and Digital Strategy: complete filming, agree posting dates and start posting where relevant
Project Milestones
Stage | Milestone | Due Date |
---|---|---|
Execute | IT & Library Readiness Weekly Reporting Begins | 05-Aug-2024 |
Execute | Welcome Week Planning Complete (D1.3, D1.4, D1.5a, D1.5b, D1.6, D1.8, D1.9, D1.10) | 19-Aug-2024 |
Execute | IT & Library Readiness Weekly Reporting Ends | 06-Sep-2024 |
Deliver | International Arrival and Start of Welcome Week (External Milestone) (D2.1) | 07-Sep-2024 |
Deliver | Start of Teaching Week 1 (External Milestone) | 18-Sep-2024 |
Deliver | Start of Teaching Week 2 (External Milestone) | 25-Sep-2024 |
Deliver | Delivery Sign Off Review following Start of Session | 17-Oct-2024 |
Close | Project Closure | 02-Dec-2024 |
- Approved budget
- 75.0 days
- Activity this month
- 8.4 days
- Activity this year
- 26.9 days
- Activity to date
- 26.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 31.0 days