Project Report for November 2024
- Report Date
- November 2024
Achievements this period
- Lessons Learned reviewed
- Closure report drafted and circulated
Issues
- No issues
Next Steps
- Close the project
Milestones
Stage | Milestone | Due Date | Complete |
---|---|---|---|
Deliver | Delivery Sign Off Review following Start of Session - Major | 22-Nov-2024 | No |
Close | Project Closure - Major | 02-Dec-2024 | No |
- Approved budget
- 75.0 days
- Activity this month
- 8.4 days
- Activity this year
- 26.9 days
- Activity to date
- 26.9 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 31.0 days