Report for September 2017
- Report Date
- September 2017
Achievements
- Award made to selected vendor
- Negotiations on contract started with vendor
Issues
- Completion date extended by a few weeks
Next steps
- Complete commercial negotiations
- Continue to work through post-ITT checklist
- Plan for follow-on implementation project
Issue: Status is AMBER because final milestones have had to be pushed back by a few weeks. This extension of the milestones is because of the work required to complete negotiations with the vendor taking longer than originally estimated. This is reflected in the revised milestones, which are awaiting agreement with the project stakeholders.
Milestones
24-Oct-2017 | Contract Negotiations completed - Award made | Procure |
07-Nov-2017 | Closure report completed | Close |
- Approved budget
- 38.0 days
- Activity this month
- 2.5 days
- Activity this year
- 7.9 days
- Activity to date
- 33.5 days
- Estimate to complete current year
- 4.5 days
- Estimate to complete future years
- 0.0 days