Report for September 2017

Report Date
September 2017

Achievements

  • Award made to selected vendor
  • Negotiations on contract started with vendor

Issues

  • Completion date extended by a few weeks

Next steps

  • Complete commercial negotiations
  • Continue to work through post-ITT checklist
  • Plan for follow-on implementation project

 

Issue: Status is AMBER because final milestones have had to be pushed back by a few weeks. This extension of the milestones is because of the work required to complete negotiations with the vendor taking longer than originally estimated. This is reflected in the revised milestones, which are awaiting agreement with the project stakeholders.

 

Milestones

24-Oct-2017 Contract Negotiations completed - Award made Procure
07-Nov-2017 Closure report completed Close
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Status is AMBER because final milestones have had to be pushed back by a few weeks. This extension of the milestones is because of the work required to complete negotiations with the vendor taking longer than originally estimated. This is reflected in the revised milestones, which are awaiting agreement with the project stakeholders.
Change Status
Activity
Approved budget
38.0 days
Activity this month
2.5 days
Activity this year
7.9 days
Activity to date
33.5 days
Estimate to complete current year
4.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Student Alumni Platform Procurement (USG005)
Code
USG005
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Grant Spence
Current Stage
Close
Status
Closed
Start Date
27-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Jan-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary