Report for November 2017

Report Date
November 2017

Achievements

  • Post-ITT checklist completed
  • Planning and requirements for follow-on project started
  • Contract finalised and signed

Issues

  • None

Next steps

  • Project closure

 

Milestones

08-Dec-2017 Closure report completed Close
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
38.0 days
Activity this month
0.5 days
Activity this year
12.7 days
Activity to date
38.3 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.0 days

Project Info

Project
Student Alumni Platform Procurement (USG005)
Code
USG005
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Grant Spence
Current Stage
Close
Status
Closed
Start Date
27-Apr-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
19-Jan-2018
Programme Priority
2
Overall Priority
Normal
Category
Discretionary