This project will deliver a new platform for ThankQ CRM for Dev & Alumni.

USG012 will look at upgrading the infrastructure the ThankQ application and database sits on which is nearing end of life. This will provide a short term supported base for ThankQ to run on, whilst a procurement process to replace and implement the application is underway.

 

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
February 2020 BLUE 55.0 days 43.8 days 0.0

Project Info

Project
ThankQ Infrastructure Upgrade
Code
USG012
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Muriel Mewissen
Project Sponsor
Kate Brook
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
31-Aug-2018
Planning Date
28-Jun-2019
Delivery Date
28-Aug-2019
Close Date
21-Feb-2020
Overall Priority
Higher
Category
Discretionary