Impact

Priority and Funding

  • The Project Estimate is for 100 ISG Apps days
  • The Project Priority is HIGHER
  • This Project is partially Sponsor Funded by Communications and Marketing with contributions from ISG Apps and Senior VP

 

Impact and Dependencies

  • Failing to deliver this application will see an opportunity missed to link 2 systems already in use within the University
  • Staff in CAM will continue to update an increasing number of media mentions manually

 

Lessons learned from previous projects

  • Work already completed in EDINA for a similar task will be used as a reference throughout this project

 

Project Risks

Ref   Title  Initial Risk  Current Risk  Status  Management Approach  Risk Owner
1  CAM resource availability  GREEN  GREEN  Open  Reduce  Edd McCracken
2  Development effort larger than anticipated  GREEN  GREEN  Open  Reduce  Peter Pratt
3  Increase in budget required  AMBER  AMBER  Open  Reduce  Muriel Mewissen
4  Project Services availability  GREEN  GREEN  Open  Reduce  Muriel Mewissen
5  Research Information systems team availability  GREEN  GREEN  Open  Reduce  Damon Querry
6  Signal resource availability  GREEN  GREEN  Open  Reduce  Alan Donald
7  Software Development availability  GREEN  GREEN  Open  Reduce  Peter Pratt

Project Info

Project
Signal to PURE Application
Code
USG016
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Edd McCracken
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Aug-2020
Planning Date
12-Mar-2021
Delivery Date
29-Feb-2024
Close Date
16-May-2024
Programme Priority
3
Overall Priority
Higher
Category
Discretionary