Overview
Background
In a normal year, the University of Edinburgh staff would have approximately 12,000 mentions in the media. These mentions are manually updated in PURE - the University's Current Research Information System (CRIS). Due to the COVID-19 outbreak, the mentions for University of Edinburgh staff in the media has increased dramatically. In addition, Communications and Marketing (CAM) purchased Signal AI as a media monitoring tool. This increases the coverage to international media. As a result, 12,000 mentions were identified in March 2020 alone. This makes the manual update process infeasible.
This project will take an CSV output from Signal AI and convert this into a format that can be uploaded into PURE.
Scope
The Scope of this project will include -
- The development of an application to load information produced by Signal in PURE.
Out of scope
- A fully automated process
- Mentions from any other source than Signal
Objectives and Deliverables
ID | Description | Priority | Owner |
---|---|---|---|
O1 | Application to take data from Signal AI and convert into format fit for upload into PURE | ||
O1D1 | Import CSV file from Signal | Must Have | Development Team |
O1D2 | Read People and Publishers from PURE API | Must Have | Development Team |
O1D3 | Match People and Publishers by name | Must Have | Development Team |
O1D4 | Create PURE XML Upload file | Must Have | Development Team |
O2 | Establish regular upload cycle to PURE | ||
O2D5 | Provide monthly XML files to PURE for Upload | Must Have | CAM |
O2D6 | Produce Success/Failure Report to identify any cases for manual update | Must Have | PURE Service Management Team |
O3 | Agree support for API | ||
O3D7 | OLA | Must Have | Production Team |
Benefits
- Release of time and budget for CAM as the majority of media mentioned will no longer require manual updates
- Researcher media credits will be visible in PURE on a more timely basis
- REF case studies will benefit from more accurate, comprehensive and up to date media references
- Assist academics in applying for grants and promotions by being able to draw upon better media data
Success Criteria
- Researcher media mentions updates in PURE on a timely basis
- CAM staff time spent on updating media mentions in PURE reduced
Project Milestones
Stage | Milestone | Due Date |
---|---|---|
Initiate | Project Start | 21-Aug-2020 |
Plan | End of Planning | 01-Mar-2021 |
Accept | UAT Completion | 21-May-2021 |
Deliver | Delivery Sign Off | 28-May-2021 |
Deliver | Go Live | 11-Jun-2021 |
Close | Project Closure | 25-Jun-2021 |