Report for February 2024
- Report Date
- February 2024
DRAFT
Achievements
- Application deployed to live
- Post Live issue with application not running related to Bamboo Deployment plan being incorrect - updated by developer
Issues
- Main User to be created in live
Next Steps
- Complete Deployment Checklist post-Live
- Go Live
- Close Project
Milestones
Stage | Milestone | Due Date | Previous Date | Complete | |
---|---|---|---|---|---|
Deliver | Delivery Sign Off | 26-Oct-2023 | 09-Jun-2023 | No | |
Deliver | Go Live - Major | 27-Oct-2023 | 01-Mar-2023 | No | |
Close | Project Closure - Major | 31-Oct-2023 | 30-Jun-2023 | No |
- Approved budget
- 80.0 days
- Activity this month
- 3.7 days
- Activity this year
- 18.9 days
- Activity to date
- 104.6 days
- Estimate to complete current year
- 0.5 days
- Estimate to complete future years
- 0.0 days