Report for April 2004

Report Date
April 2024

DRAFT

Achievements

  • Business using application in LIVE in conjunction with Research Information Services
  • Closure Report shared with Project Sponsor

Issues

  • Post-Live issues being dealt with between service and production

Next Steps

  • Complete Deployment Checklist post-Live
  • Close Project

Milestones

Stage Milestone Due Date Complete  
Initiate Project Start - Major 21-Aug-2020 Yes

view

Plan End of Planning - Major 12-Mar-2021 Yes

view

Close Project Closure - Major 31-Oct-2023 No

view

Accept UAT Completion 08-Feb-2024 Yes

view

Deliver Go Live - Major 29-Feb-2024 Yes

view

Deliver Delivery Sign Off 27-Mar-2024 No

view

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Significant
Cost
Moderate
Scope
No Change
Overall
Significant
Has formal escalation taken place?
No
Activity
Approved budget
80.0 days
Activity this month
1.7 days
Activity this year
22.1 days
Activity to date
107.7 days
Estimate to complete current year
0.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Signal to PURE Application
Code
USG016
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Alan Donald
Project Sponsor
Edd McCracken
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Aug-2020
Planning Date
12-Mar-2021
Delivery Date
29-Feb-2024
Close Date
16-May-2024
Programme Priority
3
Overall Priority
Higher
Category
Discretionary