This project follows the completion of USG014 Development and Alumni CRM Procurement which closed in September 2020. Due to the Covid pandemic, the deployment of the selected solution was delayed and will now start from July 2021. 

This project will support:

  • the deployment of ThankQ to the Cloud
  • the migration of the data from the current onsite ThankQ instance
  • the  integration of ThankQ cloud
  • the development of the front end interfaces built on top of the new ThankQ APIs

 

 

Current project status

Report Date RAG Budget Effort Completed Effort to complete
October 2021 GREEN 0.0 days 0.0 days 0.0

Project Info

Project
Development & Alumni CRM deployment
Code
USG019
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Susan Ridder-Patrick
Project Sponsor
Kate Brook
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
05-Jul-2021
Planning Date
24-Sep-2021
Delivery Date
27-May-2022
Close Date
29-Jul-2022
Overall Priority
Normal
Category
Discretionary

Documentation