Annual project to deploy a call centre to provide support for SQA and A Level results days admission queries and Clearing 2024.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
August 2024 GREEN 50.0 days 26.5 days 5.0

Project Info

Project
Results Days and Clearing Helpline 2024
Code
USG026
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Ailsa Glass
Project Sponsor
Katrina Castle
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
12-Feb-2024
Planning Date
31-May-2024
Delivery Date
16-Aug-2024
Close Date
13-Sep-2024
Programme Priority
7
Overall Priority
Higher
Category
Compliance

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.