This project follows on from USG019 Development & Alumni CRM deployment which migrated the D&A CRM to the cloud, developed integrations and front-end interfaces. This project closed in March 2023 with some additional functionality items (Should) remaining to be added. Since then, a list of change requests and improvements has also been gathered by D&A. This project has been assigned a small amounts of funding this session to carry out as much of these items as possible. The list has been prioritised by D&A and implementation will proceed in an Agile way to address as many items as can be done within the budget constraint. An follow continuous improvement project is planned for next session (24/25) and will deal with any items left on this list and/or any new request for change from the users.

Current project status

Report Date RAG Budget Effort Completed Effort to complete
April 2024 GREEN 0.0 days 3.6 days 6.8

Project Info

Project
D&A Portal Continuous Improvements 23/24
Code
USG027
Programme
USG Portfolio Projects (OTHUSG)
Management Office
ISG PMO
Project Manager
Anna Forostianko
Project Sponsor
Kate Brook
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
04-Mar-2024
Planning Date
19-Mar-2024
Delivery Date
15-May-2024
Close Date
31-May-2024
Programme Priority
6
Overall Priority
Normal
Category
Discretionary

Documentation

Project Dashboard

Project journal

No entries found.

Change dashboard

Nothing to report.