Achievements this period

  • Consolidated findings from meetings with suppliers and customers into an interim report.
  • This achieves the deliverable for the first phase of the project

Issues

  • It is not clear if there is a benefit in progressing to the second phase of the project, the building of a prototype chatbot system. The scale of this would be extremely small based on the budget available. Additionally the resources required to build and run a system that delivered any business benefit is probably beyond what can be done under this project. In order to develop something useful we would need to identify a self contained area that generated a significant volume of very straight forward queries. I have not found a subject area within my own section that lends itself to this work. I am currently discussing with Barry Croucher if there is anything on the library side which suits.

Targets next period

  • Review current support services to establish if there is a roll for a small scale prototype system.
  • Decide if the second phase of the project should be run
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
AMBER
Overall
AMBER
RAG Commentary
Need to decide if there is a benefit in moving to phase two of the project
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
AI and Chatbots for Customer Support
Code
USI013
Programme
Z. IS Innovation - User Services (USI) - Closed
Management Office
ISG PMO
Project Manager
Neil Bruce
Project Sponsor
Gosia Such
Current Stage
Close
Status
Closed
Start Date
13-Nov-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
30-Apr-2018
Overall Priority
Normal

Documentation

Not available.