Report for April 2019

Report Date
April 2019

Achievements

  • A design solution for a prototype representation of card identity on phone based on feedback from user research and stakeholder meeting has been agreed with Apps Developer Michael Sun ( usi016_id_on_phone_design_3.pdf)

Issues

  • No issues

Next Steps

  • Michael Sun will commence work on the design beginning of June working part-time on the project to end of July
  • Budget Information (what has been spent to date and expected spend until completion

Budget Information

  • There has been no expenditure in April and none expected in May: Apps development time is 20 days for June and July @ standard rate budgeted¬†20 days @ ¬£350/day = ¬£7000
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Card Services: Feasibility study of providing student identity on smartphone
Code
USI016
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Barry Croucher
Project Sponsor
Gosia Such
Current Stage
Close
Status
Closed
Start Date
10-Oct-2018
Planning Date
n/a
Delivery Date
31-May-2019
Close Date
30-Jun-2019
Overall Priority
Normal