Report for February 2019

Report Date
February 2019

Achievements

  • Project started
  • Development scoped out

Issues

  • No issues to report

Next Steps

  • Start development

Budget Information

  • to be updated
Project Status
RAG Status
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
PC Availability App
Code
USI018
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Andrew Millington
Project Sponsor
Gosia Such
Current Stage
Execute
Status
In Progress
Start Date
21-Jan-2019
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal