Report for October 13
- Report Date
- October 2013
Achievements to date
- Geir completed design work and R+D meeting held 11 October
- Build started
Issues
- The completion date takes us 6 weeks beyond what is required. Now looking at planning by prioritised objective
Next Steps
- Replan by prioritised objective
The project is green as plan in place and progress is as expected
- Approved budget
- 80.0 days
- Activity this month
- 22.4 days
- Activity this year
- 32.6 days
- Activity to date
- 32.9 days
- Estimate to complete current year
- 47.1 days
- Estimate to complete future years
- 0.0 days