Report for October 13

Report Date
October 2013

Achievements to date

  • Geir completed design work and R+D meeting held 11 October
  • Build started

Issues

  • The completion date takes us 6 weeks beyond what is required. Now looking at planning by prioritised objective

 

Next Steps

  • Replan by prioritised objective

 

 

The project is green as plan in place and progress is as expected

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
22.4 days
Activity this year
32.6 days
Activity to date
32.9 days
Estimate to complete current year
47.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly: CMS Usage Information
Code
UWP005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
29-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal