Report for November 13

Report Date
November 2013

Achievements to date

  • Build completed for all 4 objectives and signed off on 4 December 13

Issues

  • Problems with getting into test - issues with scripts caused delays to build and integration signoff plus peer testing not signed off due to developers sick leave.  Finally got scripts into test on 3 December but Integration testing has to be delayed due to holidays. Integration signoff will be split from the build/integration signoff  until wb 16 December. The delay however did allow build signoff  for all objectives,not just objectives 1 and 3.

 

Next Steps

  • Integration testing for all 4 objectives starting 12 December (after annual leave) with signoff 17 December 13
  • Acceptance testing by business wil take place 18-20 December for all 4 objectives
  • Deploy to Live 3 January 14
Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
23.4 days
Activity this year
56.5 days
Activity to date
56.8 days
Estimate to complete current year
27.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly: CMS Usage Information
Code
UWP005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
29-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal