Build completed for all 4 objectives and signed off on 4 December 13
Issues
Problems with getting into test - issues with scripts caused delays to build and integration signoff plus peer testing not signed off due to developers sick leave. Finally got scripts into test on 3 December but Integration testing has to be delayed due to holidays. Integration signoff will be split from the build/integration signoff until wb 16 December. The delay however did allow build signoff for all objectives,not just objectives 1 and 3.
Next Steps
Integration testing for all 4 objectives starting 12 December (after annual leave) with signoff 17 December 13
Acceptance testing by business wil take place 18-20 December for all 4 objectives