Report for December 13
- Report Date
- December 2013
Achievements to date
Integration testing completed on build work for all objectives on 17 December
Issues
Problems with BOXI reports on R4. Developers unable to complete building the scripts in BOXI before Christmas due to issues with its deployment in R4 therefore were unable to complete full integration testing.
Next Steps
BOXI team to iron out R4 problems - investigating 8/1/14
Integration testing for BOXI reports thereafter full integration testing sign off
Acceptance testing by business will follow integration testing signoff
Deploy to Live will follow acceptance testing signoff
Steps 2-4 are dependant on when BOXI team can resolve issues. Project is therefore Amber as we cannot replan these steps until we know when BOXI is going to be fixed. Milestones will be updated once known
- Approved budget
- 80.0 days
- Activity this month
- 6.9 days
- Activity this year
- 63.8 days
- Activity to date
- 64.0 days
- Estimate to complete current year
- 16.5 days
- Estimate to complete future years
- 0.0 days