Report for December 13

Report Date
December 2013

Achievements to date

  • Integration testing completed on build work for all objectives on 17 December

Issues

  • Problems with BOXI reports on R4. Developers unable to complete building the scripts in BOXI before Christmas due to issues with its deployment in R4 therefore were unable to complete full integration testing.

     

Next Steps

  1. BOXI team to iron out R4 problems - investigating 8/1/14

  2. Integration testing for BOXI reports thereafter full integration testing sign off

  3. Acceptance testing by business will follow integration testing signoff

  4. Deploy to Live will follow acceptance  testing signoff

Steps 2-4 are dependant on when BOXI team can resolve issues. Project is therefore Amber as we cannot replan these steps until we know when BOXI is going to be fixed. Milestones will be updated once known

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
80.0 days
Activity this month
6.9 days
Activity this year
63.8 days
Activity to date
64.0 days
Estimate to complete current year
16.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly: CMS Usage Information
Code
UWP005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
29-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal