Report for January 14

Report Date
January 2014

Achievements to date

  • Full Integration testing completed on 20 January - this included the BOXI reports

Issues

  • Ongoing issues with BOXI  - the  upgrade was unsuccessful and had to be restarted meaning UWP could not get access to BOXI test to begin UAT until 24 Jan. Then further patching of BOXI meant that access to test was again delayed until 31 January. UAT started on 3 February.

Next Steps

  1. UAT to be completed by 7 February

  2. Deploy to Live to be completed by14 February

  3. DSOR to be completed by 25 February

Project is green again as BOXI issues sorted and revised milestones are in place

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
80.0 days
Activity this month
6.9 days
Activity this year
67.5 days
Activity to date
64.0 days
Estimate to complete current year
13.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly: CMS Usage Information
Code
UWP005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
29-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal