Report for February 2014

Report Date
February 2014

Report by Tim Gray for Sue Woodger for February 2014

Achievements in Last Period

  • Acceptance review
  • Deployment

Issues

  •   Several issues arose during deployment. These were mainly around access and report content and have now been resolved.

Next Steps

  • Deployment review
  • Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
80.0 days
Activity this month
7.0 days
Activity this year
75.0 days
Activity to date
75.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly: CMS Usage Information
Code
UWP005
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
29-May-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
n/a
Overall Priority
Normal