Report for June 2014

Report Date
June 2014

Achievements in Last Period

  • Iteration 11 started and completed
  • Non-development iteration started and completed
  • Iteration 12 started
  • Revised project roles for product Owner and UX Lead
  • Iteration plan for 2014/15 confirmed
  • Theming work stated by Headscape
  • Solution for infrastructure issues identified and implemented on DEV, TEST and STAGING. Deployments now working.

Issues

  • I

Next Steps

  • Complete iteration 12
  • Start migration for UWP website
  • UWP website moved to LIVE infrastructure
  • Continue planning for 2014/15
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
856.0 days
Activity this month
86.0 days
Activity this year
800.0 days
Activity to date
800.0 days
Estimate to complete current year
56.0 days
Estimate to complete future years
530.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary