Report for September 2014

Report Date
September 2014

Achievements in Last Period

  • Theming work completed and BETA released
  • Iteration 13 started and competed
  • Varnish service successfully deployed to LIVE
  • The majority of infrastructure issues have been resolved
  • The core project team attended DrupalCon

Issues

  • Some minor infrastructure tweaks are on going
  • Delay in writing user stories for content types, required for MVP

Next Steps

 

  • Make UWP Beta site available through Varnish
  • Continute with Iteration 14
  • Schedule next iteration of Theming
  • Complete final preparations and release UoE Drupal distribution
Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1336.0 days
Activity this month
80.0 days
Activity this year
145.0 days
Activity to date
1020.0 days
Estimate to complete current year
350.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary