Report for November 2014

Report Date
November 2014

Achievements in Last Period

  • Iteration 16 completed
  • MVP Client released
  • Theming completed by Wunderroot
  • EdWeb Distribution work continued

Issues

  • No issues to report

Next Steps

  • Release EdWeb Distribution
  • Start and compelte Iteration 17
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1456.0 days
Activity this month
67.0 days
Activity this year
292.0 days
Activity to date
1168.0 days
Estimate to complete current year
308.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary