Report for December 2014

Report Date
December 2014

Achievements in Last Period

  • Iteration 17 completed
  • Preparation for Iteration 18
  • EdWeb Distribution work continued

Issues

  • Some modules required updating which has delayed the EdWeb Distribution

Next Steps

  • Release EdWeb Distribution
  • Start Iteration 18
  • Continue to refine and maintain backlog 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1456.0 days
Activity this month
41.0 days
Activity this year
334.0 days
Activity to date
1210.0 days
Estimate to complete current year
303.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary