Report for January 2015

Report Date
January 2015

Achievements in Last Period

  • Iteration 18 completed
  • Preparation for Iteration 18
  • EdWeb Distribution work completed and distribution released
  • Non development iteration started

Issues

  • BA is leaving project services and will be replaced by PM

Next Steps

  • Complete non development iteration
  • Start¬†Iteration 19
  • Continue to refine and maintain backlog¬†
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1674.0 days
Activity this month
110.0 days
Activity this year
403.0 days
Activity to date
1279.0 days
Estimate to complete current year
389.0 days
Estimate to complete future years
19.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary