Report for April 2015

Report Date
April 2015

Achievements in Last Period

  • Iteration 19 completed
  • Release 3 successfully deployed to LIVE
  • Iteration 20 completed
  • Wunderroot delivered Theming for Event Content type
  • Additional Developer Agnes Gajda joined project team

Issues

  • Graphic Design Lead resource removed for most of March and uncertainly around this role post May (Risk 16)

Next Steps

  • Complete iteration 21
  • Work on resolution to Graphic Design Lead role 
  • Continue to refine and maintain backlog 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1674.0 days
Activity this month
56.0 days
Activity this year
600.0 days
Activity to date
1476.0 days
Estimate to complete current year
205.0 days
Estimate to complete future years
16.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary