Report for March 2015

Report Date
March 2015

Achievements in Last Period

  • Iteration 21 completed
  • Release 22 started
  • Revised JIRA processes for back log maintenance and feedback management implementedĀ 

Issues

  • Graphic Design Lead resource has been secured until the end of May but ownership and the period between May and August remains an issue (Risk 16)

Next Steps

  • Complete iteration 22
  • Deploy release 4 to LIVE
  • Work on resolution to Graphic Design Lead roleĀ 
  • Prioritise stories for release 5
  • Continue to refine and maintain backlogĀ 
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1674.0 days
Activity this month
56.0 days
Activity this year
600.0 days
Activity to date
1476.0 days
Estimate to complete current year
206.0 days
Estimate to complete future years
16.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary