Achievements in Last Period

  • Iterations 21 and 22┬ácompleted
  • Release 4 successfully deployed to LIVE
  • Significant progress made with performance issues
  • On-going graphic design issue resolved for the project duration
  • Iteration 23 started

Issues

  • On going performance improvements are required

Next Steps

  • Complete iteration 23
  • Work with Wunderroot on code audit and performance issues
  • Continue to refine and maintain backlog for remaining 2 iterations
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1674.0 days
Activity this month
70.0 days
Activity this year
680.0 days
Activity to date
1555.0 days
Estimate to complete current year
139.0 days
Estimate to complete future years
17.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016