Report for July 2015

Report Date
July 2015

Achievements in Last Period

  • Iteration 24 completed
  • Iteration 24 successfully deployed to LIVE
  • Final iteration 25 started and completed

Issues

  • No issues to report

Next Steps

  • Devploy interation 25 to LIVE
  • Complete final non-development iteration
  • Prepare closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
1674.0 days
Activity this month
56.0 days
Activity this year
805.0 days
Activity to date
1068.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
31.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary