Report for September 2015

Report Date
September 2015

Achievements in Last Period

  • Approach on open issues agreed
  • Non-development iteration competed
  • Work around for "segmentation" issue implemented

Issues

  • No new issues

Next Steps

  • Complete Distribution Documentation
  • Implement Roll-back
  • Implement improved Healthcheck
  • Due to on-going work and open issue the project will close in November
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
Change Status
Activity
Approved budget
1718.0 days
Activity this month
9.0 days
Activity this year
48.0 days
Activity to date
1727.0 days
Estimate to complete current year
8.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary