Report for November 2013

Report Date
November 2013

Achievements in Last Period

  • Iteration 3 started and completed
  • Consultants for technical QA on-site visit completed.
  • Dates for infrastructure confirmed from Unix

Issues

  •   No issues to report

Next Steps for October

  • Iteration 4 and completion of development Phase 1
  • Start of Development Phase 2 in January
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
666.0 days
Activity this month
72.3 days
Activity this year
266.1 days
Activity to date
266.3 days
Estimate to complete current year
398.7 days
Estimate to complete future years
334.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary