Report for January 2014

Report Date
January 2014

Achievements in Last Period

  • Iteration 5 (Development phase 2) stared and completed
  • infrastructure build MySQL Dev completed

Issues

  •   No issues to date

Next Steps

  • Iteration 6
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
766.0 days
Activity this month
65.0 days
Activity this year
379.0 days
Activity to date
379.0 days
Estimate to complete current year
387.0 days
Estimate to complete future years
340.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary