Report for February 2014

Report Date
February 2014

Achievements in Last Period

  • Iteration 6 (Development phase 2) stared and completed
  • Drupal DB moved onto new Infrastructure for DEV, TEST and STAGING
  • 4 week non-development iteration started

Issues

  •   No issues to date

Next Steps

  • Iteration 7
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
766.0 days
Activity this month
84.0 days
Activity this year
466.0 days
Activity to date
466.0 days
Estimate to complete current year
298.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary