Report for March 2014

Report Date
March 2014

Achievements in Last Period

  • Non development iteration completed
  • Iteration 8 started and completed
  • Backlog review started and stories transferred to JIRA

Issues

  • Deliverables from Headscape not clarified
  • Resource availability form UWP
  • BA unavailable for several weeks
  • Infrastructure issues hampering development

Next Steps

  • Resolve infrastructure issues
  • Completed backlog review and prioritise for July launch
  • Start and complete iteration 9
  • Start non-development
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
766.0 days
Activity this month
80.0 days
Activity this year
549.0 days
Activity to date
549.0 days
Estimate to complete current year
215.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary