Report for April 2014

Report Date
April 2014

Achievements in Last Period

  • Iteration 9 started and completed
  • Non development iteration started
  • Issues with BA and Headscape resolved
  • issues with infrastructure progressed
  • Available user stories for MVP estimated
  • User stories for UWP launch prioritised

Issues

  • Resource availability form UWP
  • Infrastructure issues hampering development

Next Steps

  • Complete non-development iteration
  • Start and complete iteration 10

The project has the RAG status AMBER as the business are still working on the priorities and high-level schedule of epics for next year.

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
AMBER
Overall
AMBER
Change Status
Activity
Approved budget
766.0 days
Activity this month
71.0 days
Activity this year
628.0 days
Activity to date
628.0 days
Estimate to complete current year
151.0 days
Estimate to complete future years
0.0 days

Project Info

Project
New University-wide Web CMS
Code
UWP006
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
31-Jul-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Jan-2016
Category
Discretionary