Report for August 2017

Report Date
August 2017

Achievements in Last Period

  • Progression of Contract Agreement (SaaS agreement)

Issues

Delay in gaining sign off for the SaaS Agreement.  This is now expected 01/09/17 (see issue 11)

Next Steps

  • Contract Award

The contract at this time is due to commence on 01/08/17

Target Datesort descending Title
03-Aug-2017 Award Contract
01-Sep-2017 SaaS Sign Off
08-Sep-2017 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
5.0 days
Activity this month
4.1 days
Activity this year
4.1 days
Activity to date
112.0 days
Estimate to complete current year
1.2 days
Estimate to complete future years
0.0 days

Project Info

Project
New University Search Engine: Requirements Gathering and Procurement
Code
UWP014
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Emma Mcnab
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
04-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
22-Sep-2017
Programme Priority
1
Overall Priority
Normal
Category
Compliance

Documentation