Impact

Priority and Funding

This is a priority 3 compliance project

 

Impact and Dependencies

There are no direct dependancies from ongoing projects but the follow on implementation project is dependant on the outcomes of this project.

 

Project Risks

Ref Title Impact Probability Risk Status Risk Owner
Application resources Moderate  Low  GREEN Open  Tim Gray
Technical Complexities Moderate  Medium  GREEN Open  Mairi Fraser
Changes to Information Architecture (IA) Moderate  Medium  GREEN Open  Bruce Darby

Project Info

Project
Drupal 8 Implementation Planning
Code
UWP017
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
08-Aug-2017
Planning Date
07-Sep-2017
Delivery Date
28-Sep-2018
Close Date
11-Jan-2019
Programme Priority
2
Overall Priority
Normal
Category
Compliance

Documentation

Plan