Organisation

Work/Task Breakdown

Project Phase/Task Name

Planning

  • Produce Project Brief
  • Produce estimates
  • Produce plan
  • Planning Review
  • Identify stakeholders

Implementation

  • Plan implementation
  • Secure resources for implementation
  • Communications plan

Build

  • Load balancer changes
  • Code review/ code changes
  • Peer review
  • Build review

Integration

  • Deploy to TEST and STAGING
  • Integration Testing
  • Update TAD

Acceptance

  • UAT
  • Acceptance review

Delivery

  • Deploy to LIVE  
  • Delivery Review

Closure

  •    Produce Closure Report
  •    Closure Sign-Off
  •    Closure

Resources Skills and Cost

  • The agreed solution will require resources from Project Services, UWP and ITI.

Project Governance

This project will follow the standard project governance in Project Services.

Any changes to major milestones (Initiation, Planning, Delivery, Closure) will be approved by the Project Sponsor, Project Team and WIS.

Major milestones achievements and changes will be submitted to WIS for approval/noting as necessary.

 

 

 

 

Project Info

Project
Implement TLS for EdWeb
Code
UWP018
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
David Gibbons
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
04-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
3
Overall Priority
Normal
Category
Compliance