Report for September 2017

Report Date
September 2017

 

Achievements in Last Period

  • Build underway
  • DEV/TEST complete

Issues

  • Sorry Page not same on DEV/TEST as UAT/STAGING
  • Search issues
  • MIxed mode issues

Next Steps 

  • Resolve 'Sorry' Page issue
  • Resolve search problem
  • UAT
  • Staging 
  • Deploy
  • Closure review
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
60.0 days
Activity this month
16.8 days
Activity this year
17.7 days
Activity to date
17.7 days
Estimate to complete current year
42.1 days
Estimate to complete future years
0.0 days

Project Info

Project
Implement TLS for EdWeb
Code
UWP018
Programme
Z. ISG - University Website (UWP) (Closed)
Management Office
ISG PMO
Project Manager
David Gibbons
Project Sponsor
Stratos Filalithis
Current Stage
Close
Status
Closed
Start Date
04-Sep-2017
Planning Date
n/a
Delivery Date
n/a
Close Date
27-Oct-2017
Programme Priority
3
Overall Priority
Normal
Category
Compliance