Organisation
Work/Task Breakdown
The project will be made up of 3 development iterations, top and tailed with a foundation and maintenance iteration.
The user stories are being developed by the product owner and senior user from CAHSS, with input form developers.
Resources, Skills and Costs
This project will be delivered by a team combing of colleagues form IS APplications, University Website and Communications team and a senior user representing CAHSS. A devleoper form UWP will be embedded the core development team working on user stories alongside Apps developers.
- Project management
- Drupal development
- Business analysis
- UAT testing
The three iterations three week and one two week) will be delivered within the project budget of 50 Apps days. For more information please see the estimation log.
Project Governance
Standard programme management and WIS QA process.
Project Stakeholders
Name | Business Area | Role |
---|---|---|
Adrian Richardson | IS Applications Project Services | Developer (Project Team Member) |
Ana Heyn | IS Applications Project Services | Production Management |
Andrew Hobden | IS Applications Production Management | Production Management Reprsentative |
Billy Wardrop | University Website and Communications Team | Business technical lead (Project Team Member) |
Bruce Darby | University Website and Communications Team | Project Manager and Product Owner (Project Team Member) |
Duncan MacGruer | University Website and Communications Team | UAT (Project Team Member) |
Euan Cameron | CAHSS Web Team | Senior user (Project Team Member) |
Mairi Fraser | IS Applications Project Services | Senior developer (Project Team Member) |
Tim Gray | IS Applications Project Services | UWP Project and Programme Manager (Project Team Member) |