Report for October 2012
- Report Date
- October 2012
Achievements Last Period
- The LIVE rollout was successful.
- The deployment process was documented for future rollouts.
- Project closure
Issues
Next steps
02-Oct-2012 | Go-Live rollout. |
24-Oct-2012 | DSOR/Closure |
- Approved budget
- 24.5 days
- Activity this month
- 1.1 days
- Activity this year
- 26.0 days
- Activity to date
- 26.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days