Report for October 2012

Report Date
October 2012

Achievements Last Period

  • The LIVE rollout was successful.
  • The deployment process was documented for future rollouts.
  • Project closure

Issues

  •  

Next steps

  •  
02-Oct-2012Go-Live rollout.
24-Oct-2012DSOR/Closure

 

Project Status
RAG Status
Time
GREEN
Cost
AMBER
Scope
GREEN
Overall
BLUE
Change Status
Activity
Approved budget
24.5 days
Activity this month
1.1 days
Activity this year
26.0 days
Activity to date
26.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Polopoly Updates for Cookie Legislation
Code
UWS001
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Stephen Conlon
Project Sponsor
Dawn Ellis
Current Stage
Close
Status
Closed
Start Date
30-May-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
24-Oct-2012

Documentation