Report for October 2012
- Report Date
- October 2012
Achievements in Last Period
- In this reporting period the miles stones have been re-planned in agreement with UWS, the main reason for the re-planning was resource availability in Software Development. The analysis will now be completed by UWS in mid-January
Issues
- No issues to report at this stage
Next Steps
- In November UWS will start gather speed timings to input into the BRD.
Milestones
| Target date | Title |
|---|---|
| 15-Oct-2012 | Analysis Review |
| 31-Oct-2012 | Design Review |
| 14-Jan-2013 | Build Review |
| 21-Jan-2013 | Integration Review |
| 28-Jan-2013 | Acceptance Review |
| 04-Feb-2013 | Delivery |
| 15-Feb-2013 | Deployment Review |
| 01-Mar-2013 | Closure |
- Approved budget
- 53.0 days
- Activity this month
- 0.6 days
- Activity this year
- 4.0 days
- Activity to date
- 4.0 days
- Estimate to complete current year
- 48.5 days
- Estimate to complete future years
- 0.0 days