Report for October 2012

Report Date
October 2012

Achievements in Last Period

  • In this reporting period the miles stones have been re-planned in agreement with UWS, the main reason for the re-planning was resource availability in Software Development. The analysis will now be completed by UWS in mid-January

Issues

  • No issues to report at this stage

Next Steps

  • In November UWS will start gather speed timings to input into the BRD.

Milestones

Target dateTitle
15-Oct-2012Analysis Review
31-Oct-2012Design Review
14-Jan-2013Build Review
21-Jan-2013Integration Review
28-Jan-2013Acceptance Review
04-Feb-2013Delivery
15-Feb-2013Deployment Review
01-Mar-2013Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
53.0 days
Activity this month
0.6 days
Activity this year
4.0 days
Activity to date
4.0 days
Estimate to complete current year
48.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Ajax Enhancements
Code
UWS002
Programme
Z. ISG - University Website (UWP) (Closed)
Project Manager
Tim Gray
Project Sponsor
Dawn Ellis
Current Stage
Initiate
Status
Withdrawn
Start Date
23-Jul-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
07-Dec-2012