- Report Date
- June 2013
Achievements in Last Period
- Due to revised priorities in the programme there has been no activity this month, the milestones have been revised accordingly
Issues
Next Steps
- UAT and rework
- Acceptance review
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days