- Report Date
- July 2013
Achievements in Last Period
- UAT started
- Performance measurements taken during UAT
- UWP logged 9 JIRA with change requests
Issues
Next Steps
- Complete JIRAs and UAT
- Increase DB memory on TEST, if this proves effective memory on LIVE will also be increased
- Acceptance review
- Deploy to LIVE on 27/08/13 * Pending approval from Special CAB
- Approved budget
- 35.0 days
- Activity this month
- 2.0 days
- Activity this year
- 27.0 days
- Activity to date
- 27.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 8.0 days